Dhar To Dachnan
Dhar To Dachnan
Client Name: | PMGSY |
Value Of Contract: | Rs. 3,60,00,000 |
Length of Road: | 7 Km |
Project Start: | Nov 2012 |
Project Completion: | Dec 2013 |
MAJOR CHALLENGES
This road project was to shape up on a land full of rocks. For the project operations to start the team had to lift materials through a rocky stretch of 1.3Km land which were holding structures with non-revenue clearance. The team assigned to the project were our best men as we had to complete the work within a stipulated time frame in an unfavorable landscape which coexisted with the private structures of the external parties.
ACHIEVEMENTS
The brand was appreciated for executing and completing the project on time without compromising the standards, thereby setting a bench-mark for others.
Client Name: | PMGSY |
Value Of Contract: | Rs. 3,60,00,000 |
Length of Road: | 7 Km |
Project Start: | Nov 2012 |
Project Completion: | Dec 2013 |
MAJOR CHALLENGES
This road project was to shape up on a land full of rocks. For the project operations to start the team had to lift materials through a rocky stretch of 1.3Km land which were holding structures with non-revenue clearance. The team assigned to the project were our best men as we had to complete the work within a stipulated time frame in an unfavorable landscape which coexisted with the private structures of the external parties.
ACHIEVEMENTS
The brand was appreciated for executing and completing the project on time without compromising the standards, thereby setting a bench-mark for others.