Dhrabshalla To Bugrana
Dhrabshalla To Bugrana
Client Name: | PMGSY |
Value Of Contract: | Rs. 4,03,79,500 |
Length of Road: | 8 Km |
Project Start: | Nov 2011 |
Project Completion: | Dec 2012 |
MAJOR CHALLENGES
The road was tender and no company was willing to work on such a risky road. To add to our difficulties there was no connecting road for the team to reach the site for project execution. The height at which project machineries were operating was elevated and hazardous. Being a hilly area the project was a mix of all types of obstacles and tested the skills of all the team workers.
ACHIEVEMENTS
RKC took the initiative to work on such perilous road project. The team not only completed the road on time but is today considered as an exemplarily brand which completed such a challenging road project of the state.
Client Name: | PMGSY |
Value Of Contract: | Rs. 4,03,79,500 |
Length of Road: | 8 Km |
Project Start: | Nov 2011 |
Project Completion: | Dec 2012 |
MAJOR CHALLENGES
The road was tender and no company was willing to work on such a risky road. To add to our difficulties there was no connecting road for the team to reach the site for project execution. The height at which project machineries were operating was elevated and hazardous. Being a hilly area the project was a mix of all types of obstacles and tested the skills of all the team workers.
ACHIEVEMENTS
RKC took the initiative to work on such perilous road project. The team not only completed the road on time but is today considered as an exemplarily brand which completed such a challenging road project of the state.